The Workload Planner in Fogwing CMMS provides a centralized, calendar-based view of work orders assigned to different users within an organization. It helps maintenance managers, supervisors, and administrators monitor scheduled maintenance activities and understand how work orders are distributed across the maintenance team.
​

Using the Workload Planner, users can view work orders scheduled for individual team members across different days of the week. The planner also provides visibility into each user's work allocation, making it easier to monitor assigned workloads and coordinate maintenance activities.
​
Note: The Workload Planner feature is currently accessible to users with Admin, Manager, and Supervisor roles in Fogwing CMMS.
​

1. How do we access Workload Planner in the Fogwing CMMS Platform?

Follow the steps below to access Workload Planner in Fogwing CMMS:

1. Log in to your Fogwing CMMS account by visiting https://cmms.fogwing.net/
​

2. Once you are logged in, navigate to the Workload Planner option available in the left-side navigation menu.
​


3. You can also access the Workload Planner through the Settings menu. Navigate to Settings → Maintenance Management → Workload Planner to access the feature.


3. Click on the Workload Planner icon, You will be navigated to the Workload Planner dashboard.

2. Understanding the Workload Planner Dashboard

Once you access the Workload Planner, you will be able to view the calendar-based dashboard displaying maintenance personnel and their assigned work orders.
​

The dashboard provides a consolidated view of scheduled maintenance activities across different days of the week.
​

Plant Selection

At the top-left corner of the Workload Planner dashboard, you will find the plant selection dropdown.

  1. Click on the plant dropdown.

  2. Select the required plant from the available list.

  3. The Workload Planner will display the relevant workload information based on the selected plant.

Select All Plants to view workload information across all plants.
​

Show Upcoming Preventive

The Show Upcoming Preventive option allows users to display upcoming preventive maintenance activities in the Workload Planner.

  1. Locate the Show Upcoming Preventive toggle at the top of the dashboard.

  2. Enable the toggle to display upcoming preventive maintenance activities.

  3. Review the upcoming preventive maintenance schedules in the planner.

This option helps maintenance teams keep track of upcoming preventive maintenance activities and plan their resources accordingly.


Calendar Navigation

The Workload Planner provides calendar navigation options to view work orders scheduled for different dates and weeks.

The following options are available:

  • Previous: Click the left arrow to navigate to the previous week.

  • Next: Click the right arrow to navigate to the following week.

  • Today: Click the Today button to return to the current date.

  • Calendar: Click the calendar icon to navigate to a specific date.


3. How to Edit and Execute a Work Order from Workload Planner

Fogwing CMMS allows users to edit existing work orders directly from the Workload Planner. Users can update the work order's target date, change the assigned maintenance personnel, and navigate directly to work order execution.

  1. Navigate to the Workload Planner.

  2. Locate the required work order in the calendar.

  3. Click on the work order card.

  4. A work order details window will appear.


Changing the Work Order Target Date

The Workload Planner allows users to change the target date of an existing work order. To update the target date:

  1. Click on the required work order card.

  2. The work order details window will appear.

  3. Click on the Edit button.

  4. Update the Target Date as required.

  5. Save the changes.


Changing the Assigned Maintenance Personnel

Users can also change the maintenance personnel assigned to an existing work order. To change the assigned person:

  1. Open the required work order from the Workload Planner.

  2. Click on the Edit button.

  3. Navigate to the assignment details.

  4. Select the appropriate assigning type:

    • Individual

    • Team

  5. Select the required maintenance personnel or team.

  6. Save the changes.


Executing a Work Order

You can also navigate directly to work order execution from the Workload Planner.

  1. Click on the required work order card.

  2. In the Work Order Details window, click Go To Execute WO.

  3. You will be redirected to the work order execution page, where you can proceed with the execution activities.


For any feedback or inquiries regarding the Workload Planner functionality in Fogwing CMMS, please contact our support team at [email protected].